Process

Two to three years, in five phases

Here is what happens in each phase, how long it takes and what you get at the end of it. The permit and the building work take almost half; we tell you so on day one.

Weeks, from the first visit

  1. 1Site visit and sun study1 week
  2. 2Sketch design and model6 weeks
  3. 3Planning drawings and permit8 weeks + the council
  4. 4Construction drawings8 weeks
  5. 5Site supervision12 to 18 months
  1. 01

    Site visit and sun study

    We walk the plot at two times of day, measure the neighbours and draw the shadows of both solstices.

    1 week

    Model on drawings with a cast shadow
  2. 02

    Sketch design and model

    Two or three options in plan and a card model you can take home and put in your own window.

    6 weeks

    White architectural model casting a long shadow
  3. 03

    Planning drawings and permit

    The drawings the council needs. We submit them and answer every request until the permit is granted.

    8 weeks + the council

    Hands drawing on a sheet with set squares
  4. 04

    Construction drawings

    Every detail at 1:20 and 1:5, the measurements and the budget the builders will quote on.

    8 weeks

    Hands drawing with a scale ruler
  5. 05

    Site supervision

    A visit every week, minutes every week, and the final certificate at the end.

    12 to 18 months

    Renovation site with props and rubble
Building under construction with scaffolding

On site, every week

One of us visits every Tuesday morning. You get the minutes the same day: what was built, what was decided, what it costs, and the photos.

  • Weekly minutes with photos
  • Monthly cost report against the budget
  • Final certificate and the as-built drawings